Shaft-grouted bored pile – a practical engineering approach to the bearing capacity

Shaft grouting, a technique pioneered in offshore foundation applications, has proven to be an effective method for restoring side friction between bored piles and surrounding soil. This process involves injecting cement slurry through prefabricated steel tubes attached to the pile cage.
13/12/2024 Read more

Contractor received special permit to exploit sand mines for the construction of the Cao Lanh - An Huu expressway project

On May 16th, 2024, in Dong Thap, the first two sand mines (namely Tan Thuan Dong and Thuong Lac) were granted a special mechanism to serve the Cao Lanh - An Huu expressway project. The component 1 of this expressway passes 16 kilometers through Dong Thap province, with a total...
18/05/2024 Read more

Ho Chi Minh city's Ring Road 3 is a strategic traffic axis, creating a premise to remove bottlenecks and opening up new directions

Ring Road No.3 is a crucial transportation artery. Its construction will eliminate traffic bottlenecks and unlock new opportunities for urban, industrial, commercial, and service development of Ho Chi Minh City and its neighbouring provinces. This progress follows the city's successful...
16/02/2024 Read more

Cao Lanh - An Huu expressway project needs more money for phase 1, according to the Ministry of Transport's statement

The Ministry of Transport submitted a proposal to the Prime Minister for adjusting the investment for the first phase of the Cao Lanh - An Huu expressway project. They requested an increase in the total investment capital to VND7,496 billion (US$309 million), which is VND1,610 billion...
25/12/2023 Read more

Accelerate the completion of the 50,000 DWT Chu Lai Port for operation starting in the second quarter of 2024

Construction began on March 24th, 2019. As of now, the 50,000 DWT port structure is 83% complete. The leveling and foundation work of phase 2 is nearly 90% finished, and pile construction is 98% complete. Additionally, the depth in front of the wharf has been increased to -11.6 meters...
22/11/2023 Read more

Chu Lai Port, a member of THILOGI, is undertaking significant infrastructure development, including construction of a new 365-meter wharf

Chu Lai Port, located in Chu Lai Open Economic Zone, Quang Nam, was invested in construction in 2010 and officially inaugurated and put into operation in May 2012 on an area of ​​140 hectares. This is a general cargo port with specialized subdivisions, serving both THACO's production and business...
09/06/2023 Read more

Piling works for the Long Thanh international airport's passenger terminal is completed, one month ahead of schedule

On September 15th 2022, Airports Corporation of Vietnam (ACV), the investor of Long Thanh International Airport, announced the piling completion for the foundation of passenger terminal, one month ahead of schedule. This achievement was accomplished after just 5 months...
15/09/2022 Read more

The progress of Thu Thiem 2 Bridge construction project is falling further behind schedule due to delays in site clearance.

Construction of Thu Thiem 2 bridge began in 2015, with an initial target completion date of 2018, however the project faced delays in site clearance and wasn't finished. The 885.7-meter cable-stayed bridge stretches across the Saigon River, featuring a main support tower reaching 113 meters and...
15/03/2021 Read more